Brief Description: Continued rivet work on Right wing.....
continued setting rivets and bay by bay closing up the Right wing as I did on the left. I spent some time researching the electrical routings and conduit requirements I was unsure about for this wing (having hoped to get the electrician out to confirm things before closing up the wing) and satisfied myself of a method used by a fellow builder with the same set up and installations as we have.
I replicated his conduit installation and wire routing and continued rivet setting working from the tips towards the root this time to delay closing up the electrical installation area (at the bellcrank and piot) despite my having resolved that issue I just continued rivetting in that direction.