Date:  4-21-2018
Number of Hours:  5.00
Manual Reference:  F4, F5
Brief Description:  Controls

Plans:
1. Remake and install torque tube.
Status: Complete.
2. Construct Joystick.
Status: 90% Complete. The piece parts have been formed, drilled and painted. I need to let the paint dry this week, after that they can be assembled. I elected to replace the aluminum gussets with steel gussets. There was a reported failure of the aluminum ones. The community recommends this change.
3. Install Torque Tube.
Status: Complete. The tube is finished and fits perfect. Next however I will need to cut the floorboard thru holes for the hardware to pass.
4. Apply final varnish coat to floorboard.
Status: Complete. This is the final (second) coat on the top surface. Another week to dry then I will install it.
' style=

Fabricating Steel Stick Gussets

Fabricating Steel Stick Gussets

' style=

Joystick Assembly

Joystick Assembly

' style=

Test Fitting Controls

Test Fitting Controls