Date:  2-10-2018
Number of Hours:  4.50
Manual Reference:  
Brief Description:  Rudder & Vert Stab

Plans:
1. Complete vertical stabilizer.
Status: Complete. I was unhappy with the connection of the V.S. to the fuselage. I decided to remake the connector. Basically I found that the thru-hole for the bolt did not have enough material remaining to safely secure the V.S. The solution was to simply enlarge the surface of the connector. I also formed it to the contour of the mating member. Following that I connected the remaining ribs into the correct shape.

After completing the V.S. I decided to finish the job by fabricating the brace cables. They went together fairly quickly.
' style=

Stabilizer Connection to Fuselage

Stabilizer Connection to Fuselage

' style=

Horizontal Bracing

Horizontal Bracing

' style=

Completed Empennage

Completed Empennage

' style=