Plans: 1. Install air filter and oil Status: Complete. 2. Replace the engine ground lug with a flange bolt. Status: Complete. 3. Complete the engine electrical wiring. Status: Complete. The last of the engine wiring was completed. The starter switch and tachometer were installed and continuity tested. But for a transponder and ADS-B equipment everything is ready to go. 4. Fabricate the radiator mount. Status: 10% complete. Uprights to mount the radiator were fabbed and mated to the engine at the mounting lugs. Unfortunately they will need to be scrapped. It turns out that the bolt holes I tied into were not placed as parallel as I thought. The result is the uprights are not parallel. I also noted that the mount will be dangerously close to the exhaust. So a do-over is in order.