Date:  4-29-2017
Number of Hours:  0.00
Manual Reference:  
Brief Description:  Install Lighting

Plan:

1. Add hanger lighting.

Status: Complete. Assembled and erected 2 hanger overhead lights on EMT conduit into 4 cement footings. Bolted the conduit using simple sleve made from AS pipe. The setup is unstable and needs additional weight and bracing. Will finish next weekend.