Date:  9-17-2012
Number of Hours:  6.00
Manual Reference:  
Brief Description:  Finished empennage installation

I completed the re-installation of the tail and adjustment of the electric trim. I checked the balance on the rudder and the elevators and they were well within the limits called out in Vans final installation document. The trim was adjusted using Tim Olson's procedure. All hardware was properly torqued. The elevator pushpull tube was adjusted and final torqued. The empannage intersection fairing will be installed after the FAA inspection. The following actual measurments were made.
Elevator travel Up=28 Down=20 degrees
Rudder travel left and right = 35 degrees
Elevator trim tab right up=25 down=35
Elevator trim tab left up = 0 down = 35

Elevator balance left =11.5 in/lbs
Elevator balance right = 10.5 in/lbs
Rudder balance = 12 in/lbs