Work Logs Found: 301
Category Work Time: 1530 Hours
 Date
Hours
Work Log Summary

Details

 01-15-2021
9.00
L wing bottom skin. Finished prepping and start r

 01-14-2021
5.00
Finished prepping the bottom outboard wing skin
Details

 01-13-2021
7.00
Preped the L outboard bottom skin
Details
     

 01-12-2021
8.00
Finished Rewiring Deice CAN cables and testing

 01-11-2021
4.00
Started rewiring the Deice CAN cables for 18 Ga

 01-08-2021
9.00
Deice testing and rewire
Details

 01-07-2021
8.00
Full system test. Tail quit working in the morni

 01-06-2021
9.00
Finished running wires and making plugs

 01-05-2021
6.00
Install deice actuator status display
       

 01-05-2021
2.00
Continue pulling wire

 01-04-2021
9.00
Install Pitot tude support and plan wire runs

 01-01-2021
6.00
Installed deice unit on the L tank and tank on win
     

 12-31-2020
7.00
Prepping the fuel tank for the deice equipment

 12-30-2020
3.00
Started installing the fuel tank deice parts

 12-30-2020
4.00
Made a new magnetometer base and installed

 12-29-2020
7.00
Unpacking and inventorying the Finish Kit

 12-28-2020
9.00
Making Aileron push rods for both wings

 12-22-2020
6.00
Installed the wireing for the OATs and Magnetomete
     

 12-21-2020
1.50
Wiring up the two Magnetometers
     

 12-21-2020
6.00
Finished sealing the left fuel tank
       

 12-18-2020
9.00
Continuing sealing and riviting the left tank

 12-17-2020
7.00
Making and installing Magnetometer bracket
     

 12-15-2020
1.50
Figuring out mounting for the two Magnetometers

 12-15-2020
2.00
Deice Electrical out to the wings

 12-14-2020
5.50
sealing, riviting, and cleaning up L tank sealent

 12-11-2020
6.00
Continue riveting and tank sealing the L fuel tank

 12-10-2020
5.00
tank sealed and riveted the trough in place

 12-09-2020
9.00
Finish getting the fuel take ready to rivet

 12-08-2020
8.00
Fabricated and installed the trough bulkhead seals

 12-07-2020
5.00
Made a new trough that is 0.8" deep

 12-04-2020
9.00
Got the deice actuator trough fitted inside the ta
     

 12-03-2020
7.00
Backup power
Details

 12-02-2020
8.00
Installing trough on left fuel tank

 12-01-2020
5.00
Finished actuator fixtures. Started the trough.
     

 11-30-2020
7.00
Making wing tank deice parts
Details
       

 11-27-2020
4.00
Clekod the left fuel tank together
     

 11-25-2020
7.00
Drill, DEbure, dimple Left fuel tank parts

 11-24-2020
7.00
Designing and testing different fuel tank fixtures

 11-23-2020
3.00
Prep parts for left fuel tank

 11-23-2020
2.00
Make fuel tank deice fixture and test. Tested OK
     

 11-20-2020
5.00
Finished wiring and testing the new deice controls
       

 11-19-2020
6.00
See details
Details

 11-17-2020
7.50
Worked on forming tghe fuel tank outer skins

 11-16-2020
6.00
Second skin fixture
Details
       

 11-13-2020
6.00
Tested Deice. Worked OK. Finished L forward wing

 11-12-2020
8.00
Redid to tight brackets and installed actuators

 11-10-2020
8.00
Installed the actuator brackets in the L nose
     

 11-09-2020
7.00
Making controller door. Made target and attach br
     

 11-06-2020
7.00
Designing and making controller mounting brackets

 10-23-2020
3.00
Clekod the L forward skin

 10-15-2020
7.00
Finished riveting the top wing skin

 10-14-2020
2.00
Started riveting the top L wing skin on

 10-14-2020
6.00
Making a mock up of the fuel tank deice constructi

 06-16-2020
6.00
Finished all connections to transponder except ant

 06-15-2020
5.00
See Detailed
Details

 06-12-2020
7.00
Side panels

 06-11-2020
5.00
Continue installing side panels

 06-10-2020
6.00
Installed the right passenger seat cover panel

 06-09-2020
5.00
Finished wiring all that I could and started on pa
       

 06-08-2020
6.00
Ordering parts and continuing wireing

 06-05-2020
6.00
Wireing RS232 connections

 06-04-2020
6.00
Continue wiring CAN buss

 06-02-2020
3.00
Finish installing the wiring from the sticks

 06-01-2020
5.00
Made a wire loom for Pilot and Co Pilot sticks
     

 05-26-2020
8.00
FWF wires
Details

 05-22-2020
5.00
Continue wiring up switches

 05-21-2020
8.00

Details

 05-20-2020
9.00
See full description
Details

 05-19-2020
2.00
Worked on trying to connect VPN. Didn't work.

 05-18-2020
9.00
See detailed description
Details
       

 05-15-2020
9.00
continued avionics wiring

 05-13-2020
9.00
Wireing Alternator and Bus manager

 05-12-2020
5.00
Installed a firewall pass thru plus
Details

 05-11-2020
7.00
Finished fuel pump wireing

 05-08-2020
6.00
Started working on fuel pump wireing

 05-05-2020
3.00
Connect flaps power and position sensor

 05-04-2020
3.00
Install and seal the oil cooler holder on the fire

 05-01-2020
8.00
Installed Rudder tPanel uprim actuator wiring.
       

 04-30-2020
8.00
Continue wiring panel

 04-29-2020
7.00
Wired up contactors. Installed master and Bat sel

 04-28-2020
4.00
installed VPX. Installed panel.

 04-27-2020
8.00
panel work
Details

 04-24-2020
4.00
Tested alternative panel labeling options

 04-23-2020
8.00
Labeled most of the items on the panel

 04-22-2020
6.00
Got panel ready for covering and mostly covered
     

 04-21-2020
6.00
Continue laying out and drilling holes in the pane

 04-20-2020
8.00
Layi0ut and cut holes for switches and EFII displa
     

 04-17-2020
6.00
Made and tapped a ground plate. Painted subpanel
     

 04-15-2020
8.00
EIS, backplates, and relay holder
Details
       

 04-14-2020
2.50
Started designing a holder for the EIS box

 04-13-2020
2.50
Installed flap position sensor
     

 04-10-2020
6.00
Install flap system
     

 04-08-2020
8.00
Worked on installing controll tubes and stick

 04-07-2020
8.00
Baggage door
Details
       

 04-03-2020
4.00
Riveted half lthe baggage door
     

 04-02-2020
8.00
Buss Mgr bracket. Switch layout. Start baggage Dr.

 03-31-2020
4.00
Wrapping center dadio stack
     

 03-31-2020
3.00
Modified and wrapped Throttle and Prop brackerts
     

 03-30-2020
8.00
Riveted covering and cut out openings
     

 03-28-2020
2.50
covering the center c onsole radio stack
     

 03-27-2020
8.00
Continue working on makinmg the radio stack

 03-25-2020
8.00
Continue working on the radio stack center console

 03-24-2020
8.00
Framework of center console radio rack
     

 03-18-2020
4.00
Transponder rack
Details
       

 03-17-2020
6.00
Developing and making transsponder brackets

 03-16-2020
4.00
Finished cutting out the G3X panel openings
       

 03-15-2020
8.00
Making land installing structural supports in Pane

 03-10-2020
7.00
Worked on stiffening the fold down instrument pane

 03-09-2020
8.00
Installed battery contactors plus work on panel
Details
       

 03-06-2020
8.00
Deice controller install
Details
       

 02-19-2020
4.00
Installed fuel lines from tunnel to aircraft skin
     

 02-18-2020
5.00
Installed a new parking brake acuator and pumps

 02-17-2020
4.00
Installed battery cables thru firewall

 02-14-2020
2.00
Install AHRS bracket
     

 02-04-2020
9.00
Rudder peddles and the remaining brake lines.
     

 02-03-2020
3.00
dudder peddles and brake lines

 01-31-2020
8.00
Brake and fuel lines instulation.
     

 01-30-2020
4.00
Continued working on the parking brake and rack

 01-29-2020
8.00
See details
Details
     

 01-28-2020
3.00
Started testing electric parking brake actuator

 01-27-2020
9.00
Making new fuel lines. Didn't like Fridays attemp
     

 01-24-2020
8.00
Continue working on fuel lines

 01-23-2020
3.00
Designing the fuel pumps and filters layout

 01-22-2020
4.00
Brake lines and fuel selector
Details

 01-21-2020
6.00
Rudder peddles install and start brake lines
     

 01-14-2020
3.00
Finished adjusting and installing the bsaggage bac
     

 01-13-2020
3.00
Finished the other half of the back baggage wall
     

 01-10-2020
9.00
Installing skybolt quarter turn fasteners
Details
     

 01-07-2020
6.00
Continue working on the forward skin and panel

 01-06-2020
9.00
Made panel attachments
Details
       

 01-02-2020
3.50
Aligning and riviting baggage and rear seat panels

 12-26-2019
6.00
Continued with the rear seat and baggage floors
     

 12-23-2019
8.00
Baggage floor and rear seat cover ready to rivet
     

 12-20-2019
6.00
Continue working on baggage floor, rear seat floor

 12-19-2019
3.00
Preping passenger seat bottoms

 12-13-2019
5.50
Riveted the passenger floor plans down

 12-11-2019
5.00
Prep and start installing passenger floor pan

 12-06-2019
7.50
Install smuft tubes and start back seat floor
     

 11-23-2019
3.00
Finished riviting the horz stab back together

 11-22-2019
5.00
Riveting L horz stab back together

 11-21-2019
6.00
Preping L horz stab for riveting back together

 11-20-2019
5.00

Details
       

 11-15-2019
8.00
Finished prep for R Horz stab and installed. Prep
     

 11-14-2019
2.00
Preped parts for R Horz stab install

 11-13-2019
2.00
Drilled out half of horz stab to install deice
     

 09-26-2019
3.00
drilling pattern for brackets and target
       

 09-25-2019
2.00
started installing on vertical tail
       

 09-24-2019
2.00
Continue riviting the tail cone to the forward fus

 09-23-2019
2.00
Continue riviting the tail cone to the forward fus

 09-20-2019
2.00
Riveting the tail cone to thefuselage

 09-16-2019
7.00
Connect tail cone to fuselage
       

 09-12-2019
7.00
Installed fire protective blanket
     

 09-11-2019
8.00
Finishing the hinged panel
       

 09-10-2019
4.00
Working on making a hinged fold down panel

 08-21-2019
5.00
assermble the upper fuselage assembly
     

 08-19-2019
4.00
Rear air vents
Details

 08-16-2019
2.00
Started on upper forward fuselage assembly

 08-15-2019
5.00
Installed L and R steps
     

 08-14-2019
3.00
Installed the passenger fresh air vents
     

 08-12-2019
5.00
installed the landing gear brackets
     

 08-12-2019
3.00
Get stainless steel bung welded into the exhaust
     

 08-09-2019
8.00
Put in copilots floor and started on L gear suppor
       

 08-08-2019
5.00
Finish riveting sides. Install Pilot floorboard

 08-07-2019
6.00
Continue riveting side skins

 08-05-2019
8.00
Continue riveting forward and mid side skins

 08-02-2019
7.00
Installed side skins and started riveting
     

 08-01-2019
3.00
Continue riveting the forwerd longerons

 07-31-2019
3.00
start fiveting longerons to the firewall

 07-16-2019
7.50
dimpling tghe side skins and finish counterrtsinki

 07-12-2019
6.00
More drilling and countersinking

 07-11-2019
6.00
Install and match drill the forward side skin
     

 07-10-2019
6.50
Attached mid skins and match drilled
     

 07-09-2019
7.00
Install the rear seatback and the Mid cabin decks
     

 06-28-2019
9.00
Curved the 4 side skins bottoms
       

 06-27-2019
6.00
Shaping the mid and forward Longeroons

 06-26-2019
6.00
Riviting Mid and Fwd sections and Longerons
Details

 06-25-2019
1.50
Completed drilling for the Right main gear

 06-21-2019
4.50
mid seat supports and L main gear support
Details

 06-20-2019
7.50
Seat pans and side structure
     

 06-19-2019
7.00
Mated fwd land mid fuselage
     

 06-18-2019
7.00
Continue riviting
     

 06-17-2019
9.00
Riviting forward fuselage
Details
     

 06-14-2019
8.00
Rivit forward bottom skin
Details
     

 06-13-2019
5.00
Firewall cleko'd to forward bottom skin
Details
     

 06-12-2019
2.00
Fwd Fusalage Floor- set parts and start match dril

 01-02-2019
2.00
Continue working on the fwd fuselage bulkhead asm

 01-01-2019
1.50
Continue working on the fwd fuselage bulkhead asm

 12-28-2018
7.50
Fwd Fugelage bulkhead sub assembly
     

 12-11-2018
3.00
Finished riveting the Firewall section 27

 11-30-2018
2.00
Rivet in the Nose Gear Tension Fittings
     

 11-28-2018
3.00
Continue riviting onfirewall parts

 10-22-2018
2.00
Start firewall aft attachments

 10-19-2018
2.00
Finish riveting firewall

 10-16-2018
4.00
Riveting firewall

 10-09-2018
3.50
Finish countersinking and reassemble

 10-08-2018
3.00
Further prep on firewall. dimpling and countersink

 10-05-2018
3.00
Readying parts for firewall

 08-24-2018
2.00
lContinue riveting lower aft fuselage

 08-22-2018
5.00
Riveting Aft fuselage bottom skins on

 08-21-2018
5.00
Finished DCrilling, deburring, and dimpling bottom
       

 08-20-2018
6.00
Aligning and clekoing and match driling bottom ski

 08-17-2018
5.50
Riveting the last part of the aft lower fuselage
     

 08-16-2018
4.00
Started riveting aft of midsection

 08-15-2018
4.00
More mid fuselage assembly
     

 08-14-2018
8.00
Still working on mid fuselage

 08-13-2018
9.00

     

 08-10-2018
8.00
Completed the mid fuselage bulkheads

 08-09-2018
5.00
Working on the Mid section aft spar
     

 08-08-2018
6.00
Finished the forward mid fuselage bulkhead.

 08-07-2018
7.00
Added gear legs and began riviting spar
     

 08-06-2018
6.00
Assemble the Mid Fuselage Spar
       

 08-02-2018
5.00
Finished inventorying
       

 08-01-2018
6.00
Inventorying parts

 07-19-2018
2.00
Begin unpacking and inventorying
     

 05-03-2018
4.00
mak elevator push tube, and finish horz stab parts

 05-01-2018
3.00
Finish riveting the top middle section of rear fus

 04-27-2018
2.00
More riviting on the top

 04-26-2018
3.00
Begin riveting the top on the rear fuselage.
     

 04-19-2018
2.00
start riveting the rest of the horz stab together

 04-18-2018
2.00
Make and install 6ga cables in the horz stab

 04-16-2018
4.00
Installing pitch trim

 04-04-2018
2.00
Riveting rear deck

 03-30-2018
6.00
Design and mfg a bracket for the rear deice module

 03-29-2018
2.50
Mfg studs and installing same

 03-27-2018
3.00
Working on assembling the elevator trim assembly

 03-27-2018
2.00
Finish making three more stude

 03-23-2018
5.00
Completed and installed one deice atud
       

 03-22-2018
6.00
Making parts for deice connector studs

 03-21-2018
6.00
Continue making deice studs

 03-20-2018
3.00
Work on making wing studs

 03-16-2018
3.00
Finished riveting the side skins on

 03-14-2018
1.50
Continue riveting Right side

 03-09-2018
1.50
Began riveting the right side of the rear fuselage

 03-02-2018
6.00
Continue riveting the left side
     

 03-01-2018
1.00
Continue riveting

 02-28-2018
6.50
Continue riveting
     

 02-27-2018
1.50
Begin riveting it all together

 02-16-2018
3.00
Start reassembling and riviting

 02-14-2018
3.00
Finish dimpling and start reassembly

 02-13-2018
2.00
continue disassemble, deburr, and dimple

 02-12-2018
1.50
continued deburr and dimple

 02-10-2018
2.50
Continue deburr, and dimple

 02-09-2018
6.00
disassemble, deburr, and dimple

 02-08-2018
8.00
Stringeers and upper skin
     

 02-07-2018
4.00
Installed new longerons and match drilled holes

 02-01-2018
6.00
Completed rudder trim rear fuselage parts
     

 01-30-2018
6.00
Worked on the rudder trim system

 01-19-2018
3.50
Completed the rudder trim actuator install
     

 01-18-2018
4.00
Designing Rudder Trim Bracket

 01-17-2018
3.00
completed the elevator bell crank and battery box
     

 01-16-2018
4.00
converted battery box from Concord to dual EarthX

 01-09-2018
5.00
Match drilling rear fuselage

 01-08-2018
3.00
Finished installing back and front ribs

 01-05-2018
6.00
Begin clecoing together the rear fuselage
     

 01-04-2018
1.50
Longeron for rear fuselage

 12-22-2017
9.00
Begin making the ribs for the rear fuselage

 12-21-2017
6.00
Finish riveting the horz stab ribs and the rear sp
     

 12-20-2017
7.00
Continue riveting the Horz stab.
     

 12-19-2017
6.00
Begin riveting the Horz Stab
     

 12-18-2017
8.00
Countersink horz stab spars and begin riveting
     

 12-08-2017
4.00
Horz stab - finish dimpling skins and ribs

 12-07-2017
1.00
Started dimpling the Horz stab skins

 12-06-2017
6.00
Match drilling horz stab holes. make position for

 12-01-2017
6.50
Horz stab cleko'd together
       

 11-22-2017
3.00
Horz stab forward spar partially riveted
     

 11-20-2017
3.00
Working on the horz stab front spar.

 11-17-2017
5.00
Begin assembling parts for the horz stab

 11-14-2017
4.00
Installed trim tabs on both elevators
     

 11-08-2017
1.50
Finished dimpling, and using tank sealing on tabs
     

 11-07-2017
3.00
Elevator trim tabs. Flattening and start riveting

 11-06-2017
2.00
Finished Riveting the trailing edge of the L eleva

 11-02-2017
8.00
Finished riveting the R elevator
     

 11-01-2017
8.00
Working on the L elevator
     

 10-31-2017
1.50
Finish riveting the R elevator except for the trim

 10-30-2017
3.00
Finished riveting the Right elevator
     

 10-27-2017
3.50
Almost finished riveting the right elevator

 10-26-2017
4.00
Still riveting right elevator

 10-25-2017
7.00
Riveting R Horz. stabalator

 10-24-2017
2.00
Continue dimpling and countersinking R. elevator.

 10-23-2017
4.50
Dimpling and match drilling

 10-20-2017
2.50
continue match drilling elevators

 10-18-2017
0.50
Partial drilling of skin holes to size #40.

 10-11-2017
2.00
Pput skin and horns on both elevators

 10-10-2017
1.00
Continue assemb;ing the elevators

 10-02-2017
6.00
Assemblying parts for the elevators
     

 09-28-2017
1.00
deburring and prep for elevator ribs

 09-22-2017
1.00
Fiberglassing rudder top cap

 09-20-2017
4.00
Rudder bottom cap
Details
     

 09-19-2017
3.00
Rudder cap
Details

 09-18-2017
4.00
Finished rudder
Details
     

 09-14-2017
4.50
Rudder
Details
     

 09-13-2017
3.00
riveted the two sides of the rudder together
Details
     

 09-12-2017
6.00
Riveted rudder skins to the ribs
     

 09-11-2017
7.00
Rudder prep
Details
       

 09-08-2017
3.50
Finished vert stab
Details
     

 09-07-2017
3.00
Cutting and deburring parts for the rudder

 09-06-2017
6.00
Skin almost ready to install
Details
     

 09-05-2017
3.00
working on vertical stabalizer
     

 09-01-2017
3.00
Wsork on vert stab spar

 08-31-2017
4.00
Finished inventorying all the tail kit contents
     

 08-24-2017
2.00
Received tail kit box from Vans
     