 03-27-2017
8.00
First engine start. Installed fire extinguisher

 03-24-2017
7.00
Tourqued propellor. Installed spinner and seat.
Details
     

 01-18-2017
4.50
Finished installing the two cowl baffles

 01-11-2017
1.50
flox fiberglassing the lower cowl for baffling

 12-16-2016
2.50
Clean up. Fill and sand on the cowling exhaust

 12-09-2016
6.00
Work on baffling and install crank case breather

 12-05-2016
4.00
Adjusting the cowlings fitting

 12-01-2016
6.50
Body filler added and sanded for exhaust exit.
     

 11-30-2016
5.50
Installed two thirds of the baffel seals
     

 11-29-2016
4.00
Continue working on cowl exhaust and intakes.

 11-22-2016
8.00
Fiberglass plus electrical.
Details

 11-21-2016
4.00
Adjusting Pmags and installing manifoild pressure

 11-18-2016
6.00
fiberglassing exhaust fairings. Epoxying air ducts

 11-17-2016
6.00
Cowling door, exhaust farings, cowl inlet farings
       

 11-16-2016
8.00
Man Pres Sensor, Oil press sensor, oil door

 11-15-2016
6.00
Install sniffle valve, fuel relief, & Manifold pre
       

 11-14-2016
7.00
Finished installing oil cooler. Adel clamping line
     

 11-11-2016
8.00
Oil cooler and making fiberglass exhaust cowls

 11-10-2016
2.00
Final adjust and fit the engine cowls

 11-09-2016
1.00
Installed theair intake baffleing
     

 11-08-2016
7.00
Installed heating scat tube ducting
     

 11-07-2016
4.40
Fabricated and installed 4 tension rods on bafflin

 11-04-2016
9.00
connecting fuel lines and cooling tubes
       

 11-03-2016
8.00
Finish and install Alt Air Door in air intake plen
     

 11-02-2016
6.00
Design and make alternate air door
     

 11-01-2016
8.00
Installed air filter
       

 10-27-2016
4.00
Made attachment for air filter

 10-26-2016
7.50
Continuing baffle instalation

 10-25-2016
9.00
Finish installing exhaust.
       

 10-24-2016
9.00
Air duct fiberglassing andtrimming cowling for exh

 10-21-2016
7.00
More fiberglassing on intake baffle plus paint baf

 10-20-2016
7.00
Finish making baffles and undercoated
     

 10-19-2016
9.00
Woking on modifying the air intaker

 10-18-2016
3.00
More fiberglassing on the air induction

 10-17-2016
9.50
Fiberglass engine air duct. Assembling engine baff
       

 10-14-2016
5.50
Worked on filtered air to the engine

 10-12-2016
8.00
Finished and painted Left Forward baffel
     

 10-11-2016
4.50
Finishing Left front baffle
     

 10-10-2016
8.00
Making new Left front baffle

 10-07-2016
7.00
Finished clecoing the cowl.
       

 10-06-2016
6.00
Working on the cowl
     

 10-05-2016
6.00
Fitted and cleco'd on the top cowl. Started on bot
     

 10-04-2016
8.50
Installed MT prop. Continue working on cowling

 10-03-2016
4.50
Working on the air intake filter housing

 09-30-2016
5.00
Cutting cowls
       

 09-29-2016
2.00
Finishing the Fuselage to cowl hinges

 09-28-2016
5.00
L front cowling. Alternator bracket. Start cowl hi

 09-27-2016
2.00
Moved prop to hangar and unpackaged.
     

 09-27-2016
2.00
Continue work on baffling
       

 09-22-2016
4.00
Working on baffling and air filter location

 09-16-2016
7.00
Wired up the cowl flap

 09-15-2016
4.00
Worked on sorting out fluid fittings

 09-09-2016
4.00
install cowl flap - mechanically
       

 09-09-2016
5.00
Design and make electric cowl flap
       

 09-08-2016
3.00
Installed B+ wire from Alt 1. Started cowl flap

 09-07-2016
8.00
Put a new hole in firewall. Connected control cabl

 08-30-2016
5.00
Installer exhaust. Rewire wingtip light plugs

 08-29-2016
6.50
Created the bracket to hold the mixture cable
     

 08-26-2016
2.30
Continue designing & installing throttle bracket
       

 08-25-2016
8.00
Designing a throttle bracket for the engine

 08-08-2016
10.00
Completed alternator install. Cabin heat vents.
       

 08-05-2016
6.50
Manufacture and install the ships alternator brack

 07-08-2016
8.00
Mounted Engine
       

 07-06-2016
4.00
Mounted engine bracket and started nose wheel
     

 06-28-2016
7.00
Installed battery and contactors
     