Date
|
Hours
|
Work Log Summary

|
Details

|
02-19-2022
|
4.00
|
Finished tailcone
|
|
 |
|
02-18-2022
|
0.50
|
Riveted top left tailcone skin with Joel
|
|
  |
|
01-06-2022
|
1.50
|
Begin riveting aft tail cone deck
|
|
 |
|
01-03-2022
|
6.00
|
Tail cone
|
Details
|
|
|
12-28-2021
|
1.50
|
Tail cone wiring harness
|
|
  |
|
12-27-2021
|
1.50
|
Begin install of systems in tail cone
|
|
  |
|
12-26-2021
|
4.00
|
Tail cone work
|
Details
|
  |
|
12-24-2021
|
4.00
|
Rivet tail cone
|
|
|
|
12-19-2021
|
1.50
|
Riv tape rivets in tail cone in preparation of riv
|
|
  |
|
12-13-2021
|
0.50
|
Finishing riveting top tail cone skin
|
|
 |
|
12-12-2021
|
2.50
|
Begin riveting tailcon side skins and bulkheads
|
|
 |
|
12-10-2021
|
0.50
|
Started riveting top tail cone skin
|
|
  |
|
12-09-2021
|
1.00
|
Finished dimpling and prepping top tailcone skins
|
|
 |
|
12-08-2021
|
1.25
|
Dimple top tailcone skins
|
|
  |
|
12-07-2021
|
3.50
|
Tailcone work
|
Details
|
 |
|
12-06-2021
|
1.50
|
Prep aft tailcone deck part
|
|
  |
|
12-05-2021
|
5.00
|
Tailcone work
|
|
|
|
12-04-2021
|
6.50
|
Tailcone work
|
Details
|
|
|
12-03-2021
|
1.75
|
Tailcone work
|
Details
|
 |
|
12-02-2021
|
1.50
|
Prep Aft bottom skin
|
Details
|
 |
|
12-01-2021
|
3.50
|
Talicone work
|
Details
|
|
|
11-30-2021
|
4.00
|
Tailcone work
|
Details
|
|
|
11-28-2021
|
3.00
|
Tailcone work
|
Details
|
  |
|
11-27-2021
|
1.00
|
Prep battery angles
|
|
  |
|
11-23-2021
|
1.50
|
Prep and paint bulkheads
|
|
  |
|
11-21-2021
|
2.00
|
Prep bulkheads
|
Details
|
 |
|
11-20-2021
|
2.50
|
Rivet bulkhead, bullkhead prep and paint
|
|
|
|
11-20-2021
|
0.50
|
Finalze elevator riveting
|
|
  |
|
11-19-2021
|
2.00
|
Tailcone work
|
|
  |
|
11-18-2021
|
4.00
|
Bulkhead prep, paint and rivet,
|
|
 |
|
11-17-2021
|
2.00
|
Fabricate HS Stab attach bar and rudder stops
|
|
 |
|
11-17-2021
|
2.00
|
Bulkhead prep
|
|
  |
|
11-16-2021
|
1.00
|
Bulkhead to VS work
|
|
 |
|
11-15-2021
|
0.50
|
Bulkhead to VS work
|
|
  |
|
11-14-2021
|
4.00
|
Prepping tailcone parts
|
|
 |
|
11-13-2021
|
4.50
|
Elevator work
|
|
  |
|
11-08-2021
|
1.00
|
Elevator work
|
|
  |
|
11-07-2021
|
2.00
|
Elevator work
|
|
  |
|
11-06-2021
|
5.00
|
Elevator worki
|
|
  |
|
11-03-2021
|
1.00
|
Elevator work
|
|
  |
|
11-02-2021
|
1.50
|
Elevator work
|
|
  |
|
11-01-2021
|
3.50
|
Elevator work
|
|
|
|
10-31-2021
|
2.00
|
Elevator work
|
|
  |
|
10-30-2021
|
6.00
|
Elevator work
|
Details
|
  |
|
10-29-2021
|
5.00
|
Elevator work
|
Details
|
|
|
10-22-2021
|
5.00
|
Prep trim tab and left elevator skin for ribs
|
|
  |
|
10-16-2021
|
1.50
|
Elevator work
|
Details
|
  |
|
08-08-2021
|
2.00
|
Elevator work
|
|
  |
|
08-07-2021
|
4.00
|
Elevator work
|
|
  |
|
08-05-2021
|
2.00
|
Elevator work
|
|
  |
|
07-31-2021
|
3.00
|
Elevator work
|
|
  |
|
07-29-2021
|
4.00
|
Elevator work
|
|
  |
|
07-28-2021
|
2.50
|
Elevator work
|
|
|
|
07-27-2021
|
1.75
|
Elevator work
|
|
  |
|
07-26-2021
|
1.00
|
Elevator work
|
|
  |
|
07-25-2021
|
6.00
|
Elevator work
|
|
  |
|
07-23-2021
|
1.50
|
Elevator work
|
|
  |
|
07-22-2021
|
2.00
|
Elevator work
|
|
  |
|
07-21-2021
|
2.00
|
Finished HS
|
|
 |
|
07-20-2021
|
1.50
|
Continued work on HS
|
|
|
|
07-18-2021
|
1.00
|
Primed elevator parts
|
|
  |
|
07-18-2021
|
6.00
|
HS Construction
|
|
 |
|
07-05-2021
|
4.00
|
Prepped elevator ribs with Rene's help
|
|
  |
|
06-27-2021
|
2.00
|
Prepped elevator ribs
|
|
  |
|
06-20-2021
|
3.00
|
Riveted HS spars
|
|
  |
|
06-13-2021
|
5.00
|
Prepped HS spars and doublers
|
|
  |
|
06-06-2021
|
4.00
|
Prepped HS parts
|
|
  |
|
05-20-2021
|
3.00
|
Riveted parts to HS spars
|
|
|
|
05-16-2021
|
6.00
|
Prepped HS parts
|
|
  |
|
05-02-2021
|
3.00
|
Finalized rudder with Tom and Rene's help
|
|
 |
|
04-24-2021
|
6.00
|
Rudder construction
|
|
  |
|
04-21-2021
|
2.00
|
Begin rudder construction
|
|
  |
|
04-20-2021
|
1.25
|
Finalize VS construction
|
|
 |
|
04-14-2021
|
1.00
|
Continue VS construction
|
|
  |
|
04-11-2021
|
3.00
|
Continue VS construction
|
|
  |
|
04-10-2021
|
4.00
|
Continue VS construction
|
|
  |
|
04-09-2021
|
1.00
|
Continue VS construction
|
|
  |
|
04-08-2021
|
1.00
|
Continue VS construction
|
|
  |
|
04-07-2021
|
1.00
|
Continue VS construction
|
|
  |
|
04-06-2021
|
1.50
|
Continue VS construction
|
|
  |
|
04-05-2021
|
1.00
|
Continue VS construction
|
|
  |
|
04-04-2021
|
3.00
|
Continue VS construction
|
|
  |
|
04-03-2021
|
1.50
|
Begin VS construction
|
|
  |
|
04-02-2021
|
2.00
|
Inventory emp kit
|
|
  |
|
04-01-2021
|
2.00
|
Delivery of Emp kit and move to hangar
|
|
  |