RV10
Work Logs Found: 154
Category Work Time: 1682 Hours
 Date
Hours
Work Log Summary

Details

 04-12-2025
12.00
Started the layout and fitting of all the avionics

 03-22-2025
10.00
Started cutting doors and fitting

 01-02-2025
50.00
Installing door latch sytems on both doors

 12-06-2024
12.00
Received all the Garmin Avionics for the plane.

 12-03-2024
12.00
Attached Cabin Top
Details

 11-29-2024
8.00
Garmin Avionics ordered

 11-06-2024
16.00
Prepared Cabin top for paint and applied paint

 11-05-2024
4.00
Primed fiberglass tailcone top

 11-04-2024
16.00
Reinstalling controls & Fuel system after interior

 10-28-2024
28.00
Prep and paint final interior of fuse and all smal

 09-18-2024
24.00
Prep and paint of cabin top and tailcone top

 05-26-2024
24.00
Removed for painting, controls and fuel systems

 03-19-2024
24.00
Did 6 carbon fiber bid layups on BRS channels

 03-13-2024
8.00
Laid out BRS channels in the cabin top and tailcon

 12-27-2023
68.00
Cutting and fitting and drilling out cabin top for

 09-21-2023
6.00
Attachment points for chute box
Details

 09-02-2023
143.00
Completed fuse including BRS channels and bulk hea

 12-31-2022
8.00
Priming fuse small parts

 12-05-2022
24.00
Continue working on finishing fuse interior

 03-28-2022
8.00
Complete foot peddles

 03-27-2022
8.00
Foot Peddles
Details

 03-26-2022
18.00
Intalled SS fuel hoses for EFII system with return

 03-23-2022
8.00
Fuel Pumps
Details

 02-10-2022
8.00
Made support plate and mounted fuel pumps in tunne

 02-07-2022
4.00
Started installing the EFII fuel system

 01-31-2022
16.00
Attached tailcone to fuse and riveted bottom skins

 01-25-2022
6.00
Riveted the tailcone bottom skin in place

 01-17-2022
8.00
Finished riveting all tailcone assemblies

 01-10-2022
16.00
Removed all blue plastic from tailcone parts, prep

 01-03-2022
5.00
Match hole drilled right side tailcone longerons

 12-11-2021
4.00
Assembled tail cone
Details

 07-28-2021
40.00
Installed channel on right side including BRS rock

 07-25-2021
25.00
Installing left & right skin with channel
Details
       

 07-21-2021
6.00
Installing spacers on fuse
       

 07-06-2021
4.00
Primed spacers and installed on left side of fuse

 06-14-2021
8.00
Channel spacers fab.
Details

 06-10-2021
4.00
Started fabing the 3/16 alum bar spacers for the e

 06-08-2021
4.00
Cut left side skin for channels.

 06-03-2021
3.00
Continued to cut and roll harness channel
Details
       

 06-01-2021
4.00
Cutting and bead rolling harness channel.
Details

 05-27-2021
2.00
Started layout of harness channel down pilot side
Details

 03-22-2021
2.00
Prepared side skins for roll bending

 11-12-2020
16.00
Made and sent sample of install process to BRS
       

 08-27-2020
3.00
Drilling Longerons to substructure - 29-7

 08-25-2020
1.00
Baggage Door seal angle

 08-17-2020
6.00
Rolling Mid Side Skins

 08-14-2020
2.00
Fab Clamping Block

 08-13-2020
4.00
Finished bending and drilling longerons

 08-07-2020
4.00
Cutting and bending longerons

 08-06-2020
4.00
Cutting and Bending Longerons

 07-01-2020
7.00
Continuing Riveting the Bulkhead Assemblys togethe
       

 06-30-2020
7.00
Riveting the skins together to connect the Fwd and
       

 06-29-2020
7.00
Connecting the Fwd Center Section Bulkhead Assembl
       

 06-26-2020
7.00
Riveting the connecting parts to the bottom skin,
       

 06-16-2020
7.00
Working on seat brackets, and deburring holes on S
       

 06-15-2020
7.00
Clecoing the skin together after being primed, and
       

 06-11-2020
7.00
Continued work on Fuselage
     

 06-10-2020
7.00
Prepping skin and working on the seat brackets
       

 06-06-2020
1.00
Dimpling the F-1072 FWD Bottom Skin
     

 06-04-2020
7.00
Mating the Fwd Fuselage Bulkhead with the Aft Fuse
       

 06-01-2020
7.00
Continued work on the Fuselage Assembly to get rea
       

 05-28-2020
7.00
Final Drilling the holes common to the floor panel
       

 05-27-2020
7.00
Clecoing the Frames to get ready to final drill th
       

 02-22-2020
7.00
Continuing work on the Firewall
       

 07-02-2019
7.00
Riveting the skin onto the Mid Fuse Ribs
     

 07-01-2019
7.00
Begining work for the firewall.
       

 04-13-2019
4.00
Primed final parts and prepared for assembly
       

 03-20-2019
2.00
Started pre-fit ribs on rear seat subassembly

 03-15-2019
4.00
Contined work on seat sub assembly

 03-11-2019
4.00
Started Seat Rib Subassembly

 02-09-2019
8.00
Prepared and Primed all parts and marked bottom sk

 07-20-2018
18.00
Both Hunter and Logan helped finishing rear spar b

 07-19-2018
12.00
Worked on rear spar bulkhead assembly
       

 07-18-2018
12.00
Started rear spar. Primed parts

 07-17-2018
12.00
Continued work on Aft center section

 07-16-2018
12.00
Finished riveting primed parts on center bulkhead
Details

 07-11-2018
12.00
Started Riveting on F-100C-L&R supports
Details

 07-06-2018
4.00
Primed Fwd Center Section bulkhead parts

 06-28-2018
12.00
Contined work on mid fus bulkheads
Details

 06-27-2018
12.00
Started Mid Fuse Bulkheads
Details

 08-09-2017
8.00
Primed tailcone parts
Details

 08-04-2017
18.00
Tailcone work
Details

 08-02-2017
18.00
Contined work on tailcone
Details

 08-01-2017
18.00
Started Tailcone
Details

 07-13-2017
18.00
Prosealing elevator trailing edge
     

 07-06-2017
18.00
Working on elevators
     

 06-21-2017
12.00
Working on elevators

 06-19-2017
12.00
Started on elevators

 06-16-2017
12.00
Completed HS
     

 06-15-2017
12.00
Continued riveting HS skins

 06-14-2017
12.00
Continued riveting HS skins
Details

 06-13-2017
18.00
HS final riveting
Details
       

 06-12-2017
18.00
Started final assembly of HS including riveting
Details

 06-09-2017
8.00
Working on tail cone prep. Cutting , drilling, etc
Details

 06-07-2017
16.00
Finished skinning the VS
Details

 06-06-2017
18.00
Started riveting the skin
Details

 06-05-2017
18.00
Final Assembly of VS. Final Riveting
Details

 08-17-2016
9.00
Finished Inventory on Fuslage Kit

 08-15-2016
9.00
Inventoried Fuselage Kit

 08-12-2016
4.00
Picked up fuselage kit from freight lines dock

 08-01-2016
2.00
Video taped all the pre-skinned parts for AP's rev

 07-27-2016
12.00
Finished riviting the elevators for pre-skin inspe
     

 07-25-2016
12.00
Started riviting the elevators

 07-20-2016
12.00
Continued to rivit the HS

 07-15-2016
4.00
Started Riviting HS Ribs

 07-13-2016
12.00
Riviting the HS Spars

 07-12-2016
12.00
Starting Riviting the HS. Completed upto page 8-6

 07-11-2016
14.00
Started riviting the rudder.

 07-11-2016
2.00
Ordered Fuselage Kit

 07-08-2016
8.00
Finished Priming all parts
     

 07-07-2016
10.00
Bulk Primed all parts and skins for rudder, HS, &

 07-06-2016
12.00
FInished getting parts ready for prime.
     

 07-05-2016
14.00
Working on the HS - Dimple Skins and Preping parts

 06-30-2016
10.00
Fitted parts and installed in skins. started strip
     

 06-29-2016
12.00
Continued drilling and fitting parts

 06-28-2016
12.00
Fabricated Cradles
       

 06-27-2016
12.00
Back on HS - preparing parts for priming

 06-23-2016
12.00
Flipped parts over on racks and primed

 06-22-2016
12.00
Primed Rudder and Elevators

 06-21-2016
12.00
Preparing parts for priming

 06-20-2016
12.00
Alumiprep and Alodine Parts

 06-17-2016
12.00
Continued working on HS to prepare for priming

 06-15-2016
12.00
Received replacment spar so dropped back to start

 06-14-2016
12.00
Continued to work preparing parts for priming

 06-13-2016
12.00
Contintued on preparing parts and stripping blue f

 06-10-2016
12.00
Continued to work on getting parts ready for primi

 06-09-2016
12.00
Cutting ribs and other parts

 06-08-2016
12.00
While waiting on new HS spar started Elevators
     

 06-07-2016
12.00
Drilled front spar flanges with 30 drill so had to

 06-06-2016
12.00
Continued working on HS to get ready for priming

 06-02-2016
12.00
Fit up and drilling on HS

 05-31-2016
12.00
Pulled parts for HS and Started cutting stiffeners

 05-19-2016
1.00
Finished step 13 and ready for priming

 05-18-2016
4.00
Did fit up on parts and final drilling

 05-17-2016
4.00
Rib parts & stiffeners seperation & Cutting

 05-16-2016
1.00
Started Rudder / Pulled parts

 03-15-2016
8.00
Wiring Harness for Ant and Camera
     

 02-25-2016
1.00
Rudder stops & Wiring
Details

 02-13-2016
4.00
Primed Parts

 02-02-2016
4.00
Alumiprep and Alodine Parts
       

 01-09-2016
4.00
FInished all steps up to priming on VS

 01-03-2016
3.00
Dimpled Remaining Parts / RIbs

 01-02-2016
0.50
FInished Dimpled Skins

 01-01-2016
1.00
Dimpled VS skins

 11-27-2015
1.50
Final Drilled Skins

 11-20-2015
2.00
Assembled ribs and attached Skin

 11-03-2015
1.50
Spar Caps
Details

 10-15-2015
2.00
Vertical Stabilizer
Details

 09-19-2015
16.00
Synergy Air Workshop
Details

 09-18-2015
2.00
Vans Aircraft Tour
Details
       

 08-24-2015
4.00
Inventoried Kit
Details
     

 08-08-2015
4.00
Picked Up Kit at Dominion Freight Dock

 08-06-2015
4.00
Picked Kit up
Details

 07-31-2015
0.00
Kit Shipped from Vans