Date:  04-30-2016
Number of Hours:  7.00
Short Description:  Elevator V Spacing

Today, I removed the two ribs on the inside of the elevator V. The original plans and pre-punched elevator ribs and skin did not allow enough room for the rudder., So, I trimmed each side back to the edge of the original rivet holes for the ribs, then using that piece, match drilled the holes in the skin to reposition the already drilled ribs. See Image 1. I trimmed the leading wrapped edge as it now didn't match up with the holes in the spar, so I added two brackets up front to tie it all together.

When finished, I also drilled out the rivets and pealed back the leading edge to ream out the hinges to the final size, something I overlooked earlier. Tomorrow, I'll try and refit everything.















Previous Builder          Next Builder




 Recent Builder Activity
Builder Project Date Hours
Taran Laval
RV-7
05-03
389
Christian Schaerer
RV-8
05-02
81
Christopher Pryce
KR2S
05-02
554
Darren C
Legal Eagle
05-02
70
Donald Schwanke
AF 1
05-02
212
G.H. "Steve Riffe
RV8
05-02
2140
Jeffrey Hartog
Aircam
05-02
106
John Steere
Panther
05-02
1156
Martin Leroux
RV-8
05-02
743
Matthew Perroux
RV-8
05-02
512
Miles Bowen
RV-7
05-02
1492
Nathan Mullins
Long Ez
05-02
4338
Neil Rosoff
RV9A
05-02
1573
Norris Brown
RV14a
05-02
1876
Peter Calley
Sling4
05-02
952
Robert Lussow
RV-10
05-02
1232
Stuart Hutchison
F1 Rocket Sport Wing VH-FLY
05-02
2728
Thomas Baumgartner
Cherry BX-2
05-02
3446
Bob Grantham
Searey LSX -"Spirit of Mackenzie"
05-01
614
Brett Holland
SS7
05-01
186
Con Kelley
RV-7
05-01
1245
David LeFrancois
Cozy MKIV
05-01
384
Douglas Malloy
CH750 Cruzer
05-01
647
JAMES TRAYNOR
VELOCITY- XLRG
05-01
1606
John D Hazen
RV-12
05-01
657
LADD Avion LLC
RV14
05-01
26
Lloyd Swenson
RV-12
05-01
1533
Mark Jackson
RV-8
05-01
762
Michael Gugl
Lightning LSA
05-01
811
Michael McCabe
RV-14
05-01
14

Projects Uploaded: 1278
Logs Uploaded: 205576








Copyright © 2001-2016 Matronics. All Rights Reserved. Privacy Policy.